1. Consider this scenario:
A project in its 26th week has an actual cost of $270,000. It was scheduled to have spent $261,000. For the work performed to date, the budgeted value is $272,000.

  • What are the cost and schedule variances for the project?
  • What are the SPI and CPI?

2. Providing a project status is one way to report out the overall progress of a project to impacted stakeholders. Since you now are in progress with your project, use the attached Status Report Template.xlsx to complete the current status of your project, assuming you are at a point in your project further along.